Hamlet Paving Notification
Be advised that work associated with paving at Newbrook, Radway and Thorhild is scheduled to commence on October 6th, 2025.
The work is being performed by Breycon Construction Ltd, and will commence on the 6th in the Hamlets of Newbrook and Radway, then to Thorhild. The first activity will be milling the existing pavement, then laying in new hot mix asphalt. Here are the locations where the work will be performed:
- Hamlet of Newbrook: 50 Street, from 50 Avenue to just south of 51 Avenue
- Hamlet of Radway: 49 Avenue, from 51 Street to 50 Street
- Hamlet of Thorhild: 4 Avenue from 1 Street to 2 Street, curb paving on the east side of 1 Street extending from 4 Avenue to 9 Avenue.
Please do not park on the roads that have been identified while they remain under construction. If you have any questions or concerns, please contact the Public Works Office at 780-398-3977.
Your cooperation is very much appreciated.